Throughout October and November a number of schemes will take place across Derby to repair potholes. The works will involve resurfacing stretches of roads to repair potholes and prevent further ones forming – instead of simply patching the holes.

In addition, a number of joints on concrete roads in the city will be replaced in a process similar to replacing sealant in a bathroom.

This work is weather dependent and dates may change.

The schemes are being funded through the Pothole Action Fund and the work will be completed by Thomas Bow ltd on behalf of Derby City Council.

To reduce disruption to residents, some of the work will be completed at weekends and during off peak hours (9.30 am – 3.30pm).

Upcoming works:

Road Dates Details
Burton Road Saturday 2nd and Sunday 3rd November

Saturday 9th and Sunday 10th November

A signed diversion route will be in place.
Grampian Way Monday 28th – Wednesday 30th October Works will take place at the roundabout with Sinfin Lane. An off peak road closure will be in place (9.30am – 3.30pm. with diversions clearly signed.
Stenson Road Monday 4th – Thursday 7th November Works will take place near the Stenson Road rail bridge. An off peak road closure will be in place with diversions clearly signed.
Murray Road Monday 28th October – Friday 1st November and Monday 4th – Tuesday 5th November An off peak road closure will be in place but access will be maintained.
Chesterton Road Friday 1st November and Tuesday 5th November An off peak road closure will be in place.
Nevinson Drive

Ainsworth Avenue

Gaskell Drive

Wednesday 6th – Friday 8th November Works to replace joint material in road surface.